Project Overview
A contract for the construction of a 600MW module production line was signed in July 2020. The installation and commissioning of the production line will begin at the Korean project site in October. The acceptance will be completed by the end of February 2021.
Plan composition
Preliminary positioning and installation of the 600MW module production line, mid-term debugging and ramping, and later project equipment acceptance, etc.
The project only took one month from equipment positioning to the first component output, and only three months to customer acceptance. The project was implemented efficiently and with high quality.